3DM2™ Online Help

Table of Contents Previous Next Index


Maintaining Units > Scheduling Background Tasks > Adding a New Task Schedule Slot

Adding a New Task Schedule Slot
When you add a rebuild/migrate or verify task schedule, you specify the day of the week, time, and duration for the task. For self-test schedules, you specify day and time, but not duration. (Duration is not required for self-tests.)
Depending on the schedule and system workload, background tasks may require more than one scheduled duration to complete.
To add a task schedule slot
1
Choose Management >> Schedule from the menu bar.
The Scheduling page appears, showing the schedule for Rebuild/Migrate Tasks.
2
3
4
5
Click the Add New Slot button.
The page refreshes and the new schedule is added to the list.
 
Note: The scheduled tasks can be added in any order. For example a new task scheduled for Tuesday (slot-2) will preempt the task originally scheduled for Wednesday (slot-1).

Related Topics

Table of Contents Previous Next Index